Which of the following is a key principle of “Agile” project management?
সমন্বিত ২ ব্যাংক (সোনালী ও জনতা) • অফিসার (আইটি) • 2026 • 2026-01-03
ADetailed documentation is more important than working software
BFollowing a plan is more important than responding to change
Citerative development and customer collaboration
DContract negotiation is the primary goal
সঠিক উত্তর: C. iterative development and customer collaboration